Page 130 - PRESS-FIT SYSTEMS FOR DIVERSE APPLICATIONS
P. 130

3.0 TECHNICAL DATA
            SYSTEM DESIGN CONSIDERATIONS

            AND TUBE EXPANSION




            The water velocity required for flushing must be sufficient to pick up   If the pipe system is to be left empty after the pressure test, then
            and carry the majority of the dirt and debris from within the system.  a pressure test with dry air and/or inert gas should be performed,
            The hot and cold water pipelines should be flushed separately.  (microbiological contamination through bacteria and corrosion of
                                                               carbon steel systems has to be avoided).
            For details, please refer to the BSRIA Guide BG29-2012
            ’Pre-Commissioning Cleaning of Pipework Systems‘.  The pressure test should consist of two steps;
            Some contracts may still require that proprietary chemicals are used      Leak test
            to cleanse and flush pipework before full commissioning. XPress is      Tightness test
            compatible with a wide selection of products. To find out more contact   The leak test involves inspecting the system for joint integrity
            us.                                                (tightness), the tightness test focuses on checking the system for
            General Consideration                              strength.
            All items that are sensitive to sediment must remain valved off and   The tightness test with water is described in the B&ES Guide to Good
            by-passed throughout the flushing procedure. Care should be taken to   Practice TR/6, BS EN 806-4, BS6700.
            ensure that pumps are not allowed to operate against a closed head for   If pre-fabricated pipework or equipment has been hydraulically
            long periods. This situation should be avoided whenever possible.  pressure tested, off site prior to installation, this should be notified to
            CHEMICAL CLEANING                                  the cleaning/chemical treatment specialist as these may have already
            Chemical cleaning should always be carried out immediately after   developed an internal layer of corrosion, microbiological, biofilm build
            flushing.                                          up etc.
            Chemical cleaning of the system should always be the responsibility of   Due to the inherent dangers associated with pneumatic testing using
            the appointed chemical cleaning specialist and should be preceded by   inert gas or dry air a responsible person must be in charge of this
            a properly executed clean water flushing as described in the previous   operation at all times.
            section. This is an essential pre-requisite to any effective chemical   The following must be understood as a recommendation only.
            cleaning programme.                                BASIC PROCEDURE
            There are many proprietary cleaning chemicals available for preparing   If the system is to be pressure tested (as recommended) then the
            the pipework for subsequent service. Some of these are acidic, others   following procedure applies to each section in turn.
            are neutral but all must be capable of effectively removing any rust and
            other debris that has formed in the pipework prior to commissioning,   1.  Test Preparation
            without damaging the various components in the system.  a.  Check that all high points have suitable vents to facilitate removal of
                                                                  air during filling and that these are all closed.
            Strong acid cleaners that do not contain inhibitor must be avoided as
            severe internal wastage may occur, particularly at joints between tube   b.  Install suitable drainage facilities at all low points for drainage.
            and fitting.                                       c.  Blank plug or seal any open ends and close all valves at the limits of
            Irrespective of whatever cleaner is chosen, the manufacturer’s      the test section of the piping
            instructions must be followed exactly, taking particular care to ensure   d.  Remove, blank off all terminal units that may be damaged by the
            that cleaning agents are completely flushed out of the system before      test pressure.
            adding any protective inhibitors to the water.
                                                               e.  Open all valves within the enclosed test section.
            Please refer to BSRIA BG29 2012                    f.  Check that the test gauge is working correctly and has been
            ‘Pre-Commission Cleaning of Pipework Systems’.
                                                                  calibrated, and has the correct range.
            As this is specialist work, it should only be entrusted to an organisation
            that has the facilities, safety training and experience in dealing with the   g.  If the compressed dry air or inert gas is at a higher pressure than is
                                                                  required for the test (maximum 0.5bar pressure) a pressure reducing

            potentially hazardous chemicals involved. Suitably qualified personnel
            will have the knowledge to be able to offer advice on the selection        valve, pressure gauge and pressure relief valve set to open at the
                                                                  test pressure should be fitted to the connecting pipework.
            and use of appropriate chemicals, as well as the safe disposal of waste
            material.                                          h.  If possible the compressed air supply should be outside the test
                                                                  area
            PRESSURE TESTING OF PIPEWORK SYSTEMS
                                                               i.  Check that there is a suitable method for draining the system.
            It is recommended that completed pipework systems are pressure
            tested prior to being covered (insulation, or paint), and should be   It is recommended that systems be tested with a nitrogen rich (90%)/
            performed prior to commencing the cleaning procedure.   air mixture. If air is to be used it should be clean, dry and free from oil,
                                                               the drying performance should conform to ‘purity class 3 under the ISO
            The entire system should be pressure tested in accordance of BSRIA   8573’ for particulate contamination, water and oil content.
            and B&ES.
                                                               Guidance should be sought from the relevant compressor manufacturer.
            This pressure test can be both pneumatic and hydraulic and is
            determined by the installed and planned commissioning regime.



  130
   125   126   127   128   129   130   131   132   133   134   135